New Build Progress: Week 3

  • Access to the site has been made via the existing opening off Lewis Road and the contractors have started to form a new permanent access off Lewis Road.
  • The contractors are currently stripping the top-soil prior to removing from site along with the reduced level dig to the access road; they will then cut and fill the road up to the main footprint of the building.
  • Week commencing the 24th May 2010, the erection of the timber hoarding between the site and the existing schools buildings will commence. A letter has been sent to all local residents with regard to the construction work.